Putney Bridge Road Resuracing Work

It is a phased programme with total closure on Sunday 22nd February.

There will be multi-way temporary traffic signals in place from the junction of Armoury Way to the junction with Putney High Street for carriageway resurfacing works.
Phase 1 - On Monday 16/02/2015 and Tuesday 17/02/2015, from 50m west of the junction of Armoury Way to the junction Point Pleasant. Works starts from 09:00 hours to 16:00 hours.
Phase 2 - On Wednesday 18/02/2015 and Thursday 19/02/2015, from the junction of Wadham Road to St Georges Court. Works starts from 09:00 hours to 16:00 hours.
Phase 3 - On Friday 20/02/2015 and Monday 23/02/2015, from the junction of Oxford Road to the junction of Brewhouse Lane. Works starts from 09:00 hours to 16:00 hours.
Phase 4 - On Sunday 22/02/2015, Putney Bridge Road is closed fully from the junction of Armoury Way to the junction of Putney High Street. Local diversions apply. Works starts from 09:00 hours to 16:00 hours.
Phase 5 - On Tuesday 24/02/2015 and Wednesday 25/02/2015, from the junction of Putney High Street to Brewhouse Lane. Works starts from 09:00 hours to 16:00 hours.

Roehampton Resurfacing Night Works

(Sunday to Thursday only) for carriageway resurfacing works commencing from 22:00 hours to 06:00 hours on 15/02/2015 through to 12/03/2015.

A3 Roehampton Vale/A308 Robin Hood

A3 Roehampton Vale/A308 Robin Hood



Upper Richmond Road SW15
carriageway restriction with 2-way temporary traffic signals in place from the junction of Dryburgh Road to outside number 383 Upper Richmond Road for footway works commencing 12/01/2015 to 16/03/2015.

Water Leaks and Gas Escapes

Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks

WATER: 0800 714614
GAS: 0800 111999

All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.

For further information please contact the Engineer in the first instance via their telephone number, or Mr Don Ogunyemi on Tel No 020 8871 6712, Fax 020 8871 3174, E-mail dogunyemi@wandsworth.gov.uk.