Lower Richmond Road SW15 two-way temporary traffic signals outside number 205 for emergency Thames Water utility works. Estimated completion date now 09/06/2018. Contact: Thames Water 0800 009 3961.

Clarence Lane, Roehampton

28 May — 15 July

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: WORKING ON BEHALF OF THAMES WATER: SURFACE LOCATION: FW/CW

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU823H553/MHA632/Z004

Clarence Lane, Roehampton

28 May — 15 July

Delays unlikely Some carriageway incursion

Works description: WORKING ON BEHALF OF THAMES WATER: SURFACE LOCATION: FW/CW

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU823H553/MHA632/Z004

Disraeli Road, Putney

31 May — 08 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: Lay new service to 143 excavating in the nearside footway with a minimum of 1m to be maintained for pedestrians and excavating in the nearside carriageway within parking suspension,

Responsibility for works: SGN

Current status: Planned work about to start

Works reference: XW047W115290981-01228

Roedean Crescent, Roehampton

01 June — 08 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: Connections Projects:Installation of a new electricity supply for a customer:EXCAVATE AND EXPOSE MAINS CABLE FOR INSTALLATION OF A NEW ELECTRICAL SUPPLY.

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON

Current status: Planned work about to start

Works reference: EC40010747497

Roedean Crescent, Roehampton

01 June — 08 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: Connections Projects:Installation of a new electricity supply for a customer:EXCAVATE AND EXPOSE MAINS CABLE FOR INSTALLATION OF A NEW EECTRICAL SUPPLY. TEMP WALKWAY TO BE SET OUT FOR DURATION OF OUR WORKS.

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON

Current status: Planned work about to start

Works reference: EC40010746897

A3209 Putney Bridge Road,

04 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: NEW GAS CONNECTION

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB020S000000000478

Fawe Park Road, Putney,

04 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: New Gas Connections

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB020S000000000479

Woodthorpe Road, Putney

04 June — 10 July

Delays unlikely Traffic control (give & take)

Works location: Unknown

Works description: LAY 190M OF 125MM PE, ABANDON 190M OF 6" CI, COMPLETE SERVICES, MAKE 4 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT

Responsibility for works: SOUTHERN GAS NETWORKS PLC

Current status: Advanced planning

Works reference: XW053W115029798-06347

A219 Putney Hill, Putney

05 June — 08 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: OUTSIDE STOP VALVE INSTALLATION IN FOOTWAY

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU275OSV-190489-01

A3209 Putney Bridge Road

04 June — 16 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: NEW GAS CONNECTION

Responsibility for works: Wandsworth

Current status: Planned work about to start

Works reference: PB020S000000000478

B349,B306 Lower Richmond Road, Putney

05 June — 08 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Access is required to expose buried telecoms cable/duct in order to repair or replace as necessary to restore customer service

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC005DL1W00000IBU7LRPV01

B349,B306 Lower Richmond Road, Putney

06 June — 09 June

Delays likely Contra-flow

Works location: Unknown

Works description: Replace 1 jointbox frame and cover(s) (1310mm x 610mm) in Footway

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500262342202

Oxford Road, Putney

06 June — 10 June

Delays possible Traffic control (two-way signals)

Works location: Unknown

Works description: New water connection 2x32mm MDPE MTRD supplies off of 4" CI mainexcav ating 1m footway and 5m in Carriageway. Our intention is to complete the Permanent Reinstatement in the same phase

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU309000806809990045-002

A205 Upper Richmond Road, Putney

06 June — 09 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Connections Projects:Installation of a new electricity supply for a customer:EXCAVATE AND EXPOSE MAINS CABLE FOR INSTALLATION OF A NEW ELECTRICAL SUPPLY. MAINTAIN 1.2M FOR PEDS AT ALL TIMES.

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON

Current status: Planned work about to start

Works reference: EC40010748208

Hazlewell Road, Putney

06 June — 09 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Service Pipe Repair

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU302000031081378-001

Woodborough Road, Putney

06 June — 09 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: Service Pipe Repair

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU302000031083209-001

Woodthorpe Road, Putney

06 June — 09 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: Service Pipe Repair

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU302000031082231-001

A205 Upper Richmond Road, Putney

07 June — 08 June

Delays likely Traffic control (two-way signals)

Works location: Unknown

Works description: BT/Armada need to install a new phone box on the footway. 2 Way Lights will be installed for these works to be carried out.

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC005PL1W0000LOWW0046/02

A306 Roehampton Lane, Roehampton

07 June — 09 June

Delays likely Lane closure

Works location: Unknown

Works description: 10/162 TEL0182598 - Access TfL traffic signal pole 2 to install PE cell (dimmer cell), 22:00-05:00. NW/B lane 1 some C/W incursion in front of traffic signal pole. two-way traffic maintained.

Responsibility for works: Transport for London

Current status: Planned work about to start

Works reference: YG516S000000003886

Fawe Park Road, Putney

07 June — 14 June

Delays unlikely Some carriageway incursion

Works location: Unknown

Works description: Connections Projects:Installation of a new electricity supply for a customer:EXCAVATE AND EXPOSE MAINS CABLE FOR INSTALLATION OF A NEW ELECTRICAL SUPPLY. PARKING BAYS TO BE SUSPENDED. TEMP WALKWAY TO BE SET OUT FOR DURATION OF OUR WORKS.

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON

Current status: Planned work about to start

Works reference: EC40010747653

Coppice Drive, Putney

08 June — 13 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Remedial works following sewer repair works in footway

Responsibility for works: THAMES WATER

Current status: Planned work about to start

Works reference: MU026002251VQLB--000001

Earldom Road, Putney

08 June — 12 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Replace 1 jointbox frame and cover(s) (915mm x 445mm) in Footway

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500263162201

A219 Putney High Street, Putney

09 June — 11 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Connections Small Service:NEW SERVICE: (APPROX DEPTH 450mm-600mm):NEW 3PH INSTALL IN FOOTWAY - PARKING IN DISRAELI ROAD. 1.2M TO BE MAINTAINED IN F/WAY. REINSTATMENT TEAM TO STOP BEFORE BUS SHELTER AND PUT OUT CORRECT CHAPTER 8 AS PER SITE MEETING WITH SCOTT RICHARDSON

Responsibility for works: UK POWER NETWORKS EASTERN & LONDON

Current status: Planned work about to start

Works reference: EC40010747553


Putney Heath, Putney

09 June — 11 June

Delays unlikely No carriageway incursion

Works location: Unknown

Works description: Replace 1 jointbox frame and cover(s) (915mm x 445mm) in Footway

Responsibility for works: Openreach

Current status: Planned work about to start

Works reference: BC006TI001LC500262265502

 


Roehampton High Street SW15 will be closed at the junction with Roehampton Lane for TFL resurfacing works commencing 14/06/2018 to 16/06/2018 (night works only). Contact: TFL 0343 222 1234.

Rocks Lane (the bridge by Barnes Station) - will be subject to temporary 2-way traffic signals from 26 February to 10 July. Essential as Bridge will become too weak to take high level of traffic over it if nothing is done. London Buses will continue on their normal routes. The work on Rocks Lane railway bridge will see the use of temporary two way traffic signals which will be controlled manually between the hours of 7am and 7pm to prevent the traffic building up.

Water Leaks and Gas Escapes

Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks

WATER: 0800 714614
GAS: 0800 111999

All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.

For further information please contact the Engineer in the first instance or e-mail streetworks@wandsworth.gov.uk.

June 8, 2018

Bookmark and Share