Diversions and delays in the local area due to road works
Street Parties:
- Gladwyn Road - 23rd June J/W Bendemeer Road to J/W Lower Richmond Road
Rocks Lane (the bridge by Barnes Station) - will be subject to temporary 2-way traffic signals from 26 February to 10 July. Essential as Bridge will become too weak to take high level of traffic over it if nothing is done. London Buses will continue on their normal routes. The work on Rocks Lane railway bridge will see the use of temporary two way traffic signals which will be controlled manually between the hours of 7am and 7pm to prevent the traffic building up.
Gwendolen Avenue, Putney |
11 June — 26 June |
Delays possible Traffic control (multi-way signals) |
Works description: LAY 5M OF 180MM PE, ABANDON 5M OF 8" CI, MAKE 2 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT |
Responsibility for works: SOUTHERN GAS NETWORKS PLC |
Current status: Advanced planning |
Works reference: XW053W114995725-02175 |
|
Carlton Drive, Putney |
13 June — 27 June |
Delays unlikely Some carriageway incursion |
Works description: UKPN Infrastructure Works/ New Connection |
Responsibility for works: GAS TRANSPORTATION CO LTD |
Current status: Planned work about to start |
Works reference: ZP011P-00071921/R4 |
|
Carmalt Gardens, Putney |
20 June — 23 June |
Delays unlikely Traffic control (priority working) |
Works description: Service Pipe Repair |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU302000031087804-001 |
|
Disraeli Road, Putney |
20 June — 27 June |
Delays unlikely Some carriageway incursion |
Works description: Lay new service to 143 excavating in the nearside footway with a minimum of 1m to be maintained for pedestrians and excavating in the nearside carriageway within parking suspension, |
Responsibility for works: SGN |
Current status: Planned work about to start |
Works reference: XW047W115290981-01228 |
|
Earldom Road, Putney |
20 June — 22 June |
Delays unlikely No carriageway incursion |
Works description: Replace 1 jointbox frame and cover(s) (915mm x 445mm) in Footway |
Responsibility for works: Openreach |
Current status: Planned work about to start |
Works reference: BC006TI001LC500263162203 |
|
Earldom Road, Putney |
20 June — 23 June |
Delays unlikely Some carriageway incursion |
Works description: Service Pipe Repair |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU302000031088918-001 |
|
Holroyd Road, Putney |
20 June — 23 June |
Delays unlikely No carriageway incursion |
Works description: Service Pipe Repair |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU302000031078821-002 |
|
Landford Road, Putney |
20 June — 23 June |
Delays unlikely Traffic control (priority working) |
Works description: Serv Pipe Relay Ex Fitting Sz P WITHIN FOOTWAY AND CARRIAGEWAY ONLY inCarriageway. Our intention is to complete the Permanent Reinstatement inthe same phase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU302000031095381-001 |
|
Woodthorpe Road, Putney |
20 June — 23 June |
Delays unlikely Some carriageway incursion |
Works description: Rectifiy reinstatement defect in footway and carriageway in Carriageway.Our intention is to complete the Permanent Reinstatement in the samephase |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU302000031050415-001 |
|
A219 Putney High Street, Putney |
21 June — 22 June |
Delays unlikely No carriageway incursion |
Works description: Remedial works to be carried out - Remove Mod& replace with buff perfector |
Responsibility for works: SGN |
Current status: Planned work about to start |
Works reference: XW027W113806225-04067 |
Chartfield Avenue, Putney |
21 June — 28 June |
Delays unlikely Some carriageway incursion |
Works description: Connections Small Service:Disconnection / reconnection of existing electricity supply for a customer:1PH SERVICE ALTERATION IN THE FOOTWAY. PARKING BAYS TO BE SUSPENDED TO PROVIDE TEMP WALK WAY |
Responsibility for works: UK POWER NETWORKS EASTERN & LONDON |
Current status: Planned work about to start |
Works reference: EC40010748371 |
Clarence Lane, Roehampton |
28 May — 15 July |
Delays unlikely Some carriageway incursion |
Works description: WORKING ON BEHALF OF THAMES WATER: SURFACE LOCATION: FW/CW |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU823H553/MHA632/Z004 |
|
Clarence Lane, Roehampton |
28 May — 15 July |
Delays unlikely Some carriageway incursion |
Works description: WORKING ON BEHALF OF THAMES WATER: SURFACE LOCATION: FW/CW |
Responsibility for works: THAMES WATER |
Current status: Planned work about to start |
Works reference: MU823H553/MHA632/Z004 |
Holroyd Road, Putney |
11 June — 17 July |
Delays unlikely Traffic control (give & take) |
Works description: LAY 215M OF 125MM PE, ABANDON 215M OF 6" CI, TRANSFER 34 SERVICES, MAKE 2 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT |
Responsibility for works: SOUTHERN GAS NETWORKS PLC |
Current status: Advanced planning |
Works reference: XW053W115030140-02407 |
Hazlewell Road, Putney |
11 June — 11 September |
Delays unlikely Traffic control (give & take) |
Works description: LAY 600M OF 180MM PE, 50M OF 63MM PE, ABANDON 600M OF 8" CI, 50M OF 2" CI, TRANSFER 77 SERVICES, MAKE 21 MAINS CONNECTIONS AND COMPLETE ALL REINSTATEMENT |
Responsibility for works: SOUTHERN GAS NETWORKS PLC |
Current status: Advanced planning |
Works reference: XW053W115001687-02281 |
|
Water Leaks and Gas Escapes
Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks
WATER: 0800 714614
GAS: 0800 111999
All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.
For further information please contact the Engineer in the first instance or e-mail streetworks@wandsworth.gov.uk.
June 22, 2018
|