Diversions and delays in the local area due to road works
Hammersmith Bridge is closed to vehicular traffic indefinitely due to safety concerns. For further information contact the London Borough of Hammersmith & Fulham via email at bridgeproject@lbhf.gov.uk.
|
|
B349,B306 Lower Richmond Road, Putney |
07 August — 09 August |
|
|
Delays likely Traffic control (two-way signals) |
|
Works location: Unknown |
|
|
Works description: Service Pipe Repair<33mm Cway & fway in Carriageway. Ourintention is to complete the Permanent Reinstatement in the same phase |
|
|
Responsibility for works: THAMES WATER |
|
|
Current status: Planned work about to start |
|
|
Works reference: MU302000031075554-002 |
|
|
|
|
Norroy Road, Putney, |
05 August — 09 August |
|
|
Delays likely Road closure |
|
Works location: Unknown |
|
|
Works description: Remedial works to rectify core defect recieved. Relating to sewer repair works in carriageway |
|
|
Responsibility for works: THAMES WATER |
|
|
Current status: Planned work about to start |
|
|
Works reference: MU026002250ZQNR--000003 |
|
|
|
|
A219 Putney Bridge, Putney |
05 August — 05 August |
|
|
Delays possible Lane closure |
|
Works location: Unknown |
|
|
Works description: SAHARA SURVEY FOR LEAK DETECTION. NO EXCAVATION, CHAMBER OPENING ONLY |
|
|
Responsibility for works: THAMES WATER |
|
|
Current status: Planned work about to start |
|
|
Works reference: MU600PUT005-9 |
|
|
|
|
Inner Park Road, Southfields |
05 August — 21 December |
|
|
Delays possible Traffic control (multi-way signals) |
|
Works location: Unknown |
|
|
Works description: Excavate and conduct camera survey on existing 12" main to determine services& connections ahead of gas main insertion. Insert approx. 606m of new 250mm PE, make multiple major connections onto existing gas mains. Transfer/relay every service along this road onto new 250mm PE, backfill & reinstate |
|
|
Responsibility for works: SGN |
|
|
Current status: Planned work about to start |
|
|
Works reference: XW053W116415367-02523 |
|
|
|
|
|
|
A205 Upper Richmond Road, Putney |
20 July — 02 November |
Delays likely Traffic control (multi-way signals) |
Works description: Lay 24mtrs 355mm and 217mtrs 250mm PE. Abandon 241mtrs of 15" and 15mtrs 4" CI. Complete all services. Make 7 mains connections. Complete all reinstatement. |
Responsibility for works: SGN |
Current status: Advanced planning |
Works reference: XW053W116185355-05667 |
Priory Lane, |
03 August — 05 August |
|
|
Delays likely Road ahead closed |
|
Name: Priory Lane |
|
|
Location: Priory Lane |
|
|
Description: Public event - Cycling |
|
|
Responsibility for event: RideLondon |
|
|
Current status: Planned |
|
|
|
|
Richmond Park, |
03 August — 05 August |
|
|
Delays likely Road closure |
|
Name: Priory Lane |
|
|
Location: Richmond Park |
|
|
Description: Public event - Cycling |
|
|
Responsibility for event: RideLondon |
|
|
Current status: Planned |
|
|
Putney High Street SW15 lane closure outside St Mary’s Church for Thames Water utility works on 05/08/2019 and also 09/08/2019, NIGHT WORKS. Contact: Thames Water 0800 009 3961.
|
|
|
Augustus Road, Southfields |
15 July — 25 August |
Delays likely Road closure |
Works description: Excavate and expose cap end of new 250mm PE, abandon section of 12" CI. Complete all services& reinstate. |
Responsibility for works: SGN |
Current status: Planned work about to start |
Works reference: XW053W116415411-00187 |
|
|
|
Augustus Road, Southfields |
01 May — 06 October |
Delays likely Road closure |
Works description: Excavate and insert approx 500m of 250mm PE. Transfer all services and make connections onto existing gas mains. Abandon approx 500m of 12" gas main. Works to be completed in 3 phases. |
Responsibility for works: SGN |
Current status: Planned work about to start |
Works reference: XW053W116070246-00187 |
Water Leaks and Gas Escapes
Do not assume that someone else has phoned it in. Please do not report these to the Council. The following free phone numbers should be used to report leaks
WATER: 0800 714614
GAS: 0800 111999
All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.
August 5, 2019
|