Road Closures Ahead in Putney and Roehampton

Diversions and delays in the local area due to road works

Participate

Traffic and Travel Problems in Putney

Sign up for our weekly Putney newsletter

Comment on this story on the

Hammersmith Bridge is closed to vehicular traffic indefinitely due to safety concerns. For further information contact the London Borough of Hammersmith & Fulham via email at bridgeproject@lbhf.gov.uk.

Augustus Road
03 December - 04 December
Roadworks, Delays likely
Traffic management : Traffic control (multi-way signals)
Responsibility for works: UK Power Networks
Current status: Planned work about to start
Works reference:  EC40063761472

Augustus Road
03 December - 04 December
Roadworks, Delays likely
Traffic management : Traffic control (two-way signals)
Responsibility for works: UK Power Networks
Current status: Planned work about to start
Works reference:  EC40098611333

Upper Richmond Road
03 December - 04 December
Roadworks, Delays likely
Traffic management : Traffic control (two-way signals)
Responsibility for works: SGN
Current status: Advanced planning
Works reference:  XW073W119061458

Viewfield Road
03 December - 11 December
Roadworks, Delays likely
Traffic management : Road closure
Responsibility for works: Thames Water
Current status: Planned work about to start
Works reference:  MU309000811652060055-001

Arabella Drive SW15 - multi-way temporary traffic signals at the junction with Priory Lane for Thames Water utility works, commencing 03/12/2022 to 04/12/2022. Contact: Thames Water, 0800 316 9800.

Augustus Road SW19 - two-way temporary traffic signals outside & opposite number 44 for UK Power Network utility works, commencing 03/12/2022 to 04/12/2022. Contact: UK Power Network, 0800 0280 709

Danebury Avenue SW15 - multi-way temporary traffic signals with the junction of Roehampton Lane for Thames Water utility works, commencing 02/12/2022 to 04/12/2022. Contact: Thames Water, 0800 316 9800.

Disraeli Road SW15 - multi-way temporary traffic signals outside number 125 - 126 for Openreach utility works, commencing 03/12/2022 to 04/12/2022. Contact: Openreach, 0331 6689 0802

Merton Road SW18 - multi-way temporary traffic signals are currently at the junction with Replingham Road for emergency Southern Gas Network utility works, estimated date of completion 02/12/2022. Contact: Southern Gas Network, 02394 281 202

West Hill Road SW18 - two -way temporary traffic signals are currently placed outside number 67 forThames Water utility works, estimated date of completion 13/12/2022. Contact: Thames Water, 0800 316 9800. 8204

Wandsworth Bridge SW18 – Works continue on the refurbishment of Wandsworth Bridge. The on-footway cycle tracks are currently closed for pedestrians to use, due to the hoarding encroaching onto the footways both sides. There is a temporary, on carriageway, northbound cycle lane and the southbound bus lane has been widened to facilitate buses and cycles. The scope of work has recently been increased due to some additional critical works being identified on the structure and as a result the programme has been extended. Expected completion Summer 2022. Contact: Sam Emmett 0208 871 6668.

The following free phone numbers should be used to report leaks. Do not assume that someone else has phoned it in. Please do not report these to the Council.

WATER: 0800 714614
GAS: 0800 111999

All utility companies have to prioritise works across our borough as well as other boroughs in south London. The On Street Services team actively monitors works on the public highway and works with utility companies to minimise disruption as much as possible.

Like Reading Articles Like This? Help Us Produce More

This site remains committed to providing local community news and public interest journalism.

Articles such as the one above are integral to what we do. We aim to feature as much as possible on local societies, charities based in the area, fundraising efforts by residents, community-based initiatives and even helping people find missing pets.

We've always done that and won't be changing, in fact we'd like to do more.

However, the readership that these stories generates is often below that needed to cover the cost of producing them. Our financial resources are limited and the local media environment is intensely competitive so there is a constraint on what we can do.

We are therefore asking our readers to consider offering financial support to these efforts. Any money given will help support community and public interest news and the expansion of our coverage in this area.

A suggested monthly payment is £8 but we would be grateful for any amount for instance if you think this site offers the equivalent value of a subscription to a daily printed newspaper you may wish to consider £20 per month. If neither of these amounts is suitable for you then contact info@neighbournet.com and we can set up an alternative. All payments are made through a secure web site.

One-off donations are also appreciated. Choose The Amount You Wish To Contribute.

If you do support us in this way we'd be interested to hear what kind of articles you would like to see more of on the site – send your suggestions to the editor.

For businesses we offer the chance to be a corporate sponsor of community content on the site. For £30 plus VAT per month you will be the designated sponsor of at least one article a month with your logo appearing if supplied. If there is a specific community group or initiative you'd like to support we can make sure your sponsorship is featured on related content for a one off payment of £50 plus VAT. All payments are made through a secure web site.

December 2, 2022

Bookmark and Share